Let’s be a copycat

2nd place was 37,000

Not sure on how long it will take since I’m just going to do the sidewalks as I’m doing that section of building. If it was a sidewalk only kind of deal, I’m guessing 15 8 hour days. That’s two guys, both washing

1 Like

With 2 guys washing, you should be able to complete that in 5…no more than 6 days. I can do 8000ft in 8hrs by myself…have done more than that on a couple of occasions.

1 Like

Some folks just ain’t as fast as others. The curb and gutter will take us as long if not longer than the sidewalks will

I agree. I’d buy me one of those Mondos and go to town and have a helper doing the tight stuff and the curbs and gutters

You can sub it out to Jim and I for $20k:sunglasses:

4 Likes

You can use one of those cheap surface cleaners to speed those up…a BUNCH.

OR…you can do this.:grinning:

1 Like

:sunglasses: